SolarFarms.cy
Solar Park #2302 with Battery Storage — 0.825 MWp
All listings
Connection terms pending
Fully licensed
PARK-RTB-RAG2302-2026

Solar Park #2302 with Battery Storage — 0.825 MWp

Nicosia District, Cyprus
0.825 MWp
Solar
2 MWh
BESS (4h)
~10–12%
Indicative equity IRR
€190,124
Year-1 gross revenue (indicative)

Investor pack — indicative materials only; not an offer to sell securities.

Permits and licensing

Tier 1 licensed — permits in place · Land lease registered, zero encumbrances · Grid: preliminary DSO filed; formal EAC connection terms pending (offer expected Q3 2026)

Grid and timeline

Preliminary DSO application submitted; formal EAC connection offer expected Q3 2026

Target COD Q4 2026 / Q1 2027 (upon grid offer + EPC procurement)

Technical summary

Solar technology
Fixed-tilt monofacial PV, ground-mounted
BESS
Tier-1 LFP BESS, 4-hour duration (Lighthief BESS upgrade)
Annual production (indicative)
1,361 MWh/yr
Specific yield
1,650 kWh/kWp

Indicative economics

Illustrative only — not an offer. Review the investor teaser and your advisers.

ItemIndicative (€)
RTB acquisition (seller asking)€330,000
PV EPC€594,000
BESS EPC€254,000
Total indicative stack€1,178,000
Year-1 gross energy revenue (model)€190,124
Year-1 OPEX (indicative)€46,205

RTB acquisition price per seller offer (Apr 2026). BESS added by Lighthief (licence amendment required). Grid offer expected Q3 2026. Materials are indicative and confidential. Last reviewed: 2026-05-10. Lighthief Cyprus Ltd (HE 477423) — solarfarms.cy